Previous Topic

Next Topic

Book Contents

Scheduling details

Scheduling Details tab is common for any schedule task, perform the following steps after completing the Task Details entries.

  1. To set the Schedule Time, click the calendar icon, select a date and enter a time. Current date and time will be displayed as default value.
  2. To set the schedule interval, select the radio button against the desired Recurring option:
  3. Under Activate/Deactivate Task, select the radio button against Activate Task if the task has to be activated or De Activate Task if the task is desired to be activated later. In case if De Activate Task is selected, the task will remain in 'PENDING' state until activated by the user through edit operation.
  4. Click Finish. Create Task operation is completed Successfully message is displayed. The schedule is created.

    Click OK.

See also

Create Scheduler Tasks

Interpretation of Span Loss Report